The project

Consultancy Services for redesign and build of Londoon Earth Dam in Napak District

The services

Subsurface Explorations

Sample Recovery

Laboratory Testing

Report writing

The client

Ministry of Water and Environment – Water for Production

The challenge

Ministry of Water and Environment – Water for Production plans to redesign and reconstruct Londoon Earth Dam in Napak District. SADRiNE CONSULTING GROUP LIMITED was contracted to carry out geotechnical investigation for purposes of the determining the condition assessment and performance levels of the existing Londoon Dam. The aim of the investigation was to;

  • Determine geotechnical information including design parameters for the proposed foundations and any associated infrastructure.

 

project-3-1.jpg
about-img-1.jpg
home-bg-1.jpg
project-1-1.jpg
project-6-1.jpg
project-5-1.jpg
project-4-1.jpg
specialization-img-1.jpg
CTA-bg-1.jpg
previous arrow
next arrow
 

The services

Subsurface Explorations

We dug 4 trial pits to depths between 0.7 – 2 m,

Sample Recovery

We recovered disturbed samples from the bottom of each test pit and also collected construction material including clay, gravel/marram and aggregates,

Laboratory Testing

We performed laboratory testing for disturbed samples including Natural Moisture Content, Particle size distribution by Sieve analysis, Atterberg limits (Liquid, Plastic and Linear Shrinkage Limits) and for undisturbed samples including Consolidation, Permeability, and Direct Shear,

Report writing

We compiled the geotechnical investigations report comprising of our findings of the subsurface soil conditions, engineering analyses made on the laboratory tests and geotechnical parameters to be used in the design.